Aanbestedingen: Silo's

7 gearchiveerde aanbestedingen

Silo's zijn aangeschaft door organisaties als Nuon Power Generation B.V., Nuon Power Generation B.V en Gemeente Assen.
Historisch gezien zijn de leveranciers op dit gebied Aebi Schmidt Nederland BV, Geldof en Valmet Technologies OY.
  • Silo's   ⬅️

Recente aankopen van silo's in Nederland

2018-09-19   Green Heat Diemen, biomass fired Heat Only Boiler for District Heating (N.V. Nuon Energy)
This tender relates to Nuon’s intention to develop, design, engineer, construct, commission and deliver a up to 120 MW -biomass fired- heat only boiler at its existing location in Diemen, connected to the Amsterdam area district heating grid. With this new plant, Nuon aims to produce a significant amount of green heat. The heat produced by the new facility will be used to fulfil base load heat demand. Bekijk de aanbesteding »
Genoemde leveranciers: Valmet Technologies OY
2017-04-12   2017-29010 Europese aanbesteding zoutsilo (Gemeente Assen)
Voor de opslag van strooizout wordt in de gemeente Assen gebruik gemaakt van een houten silo met een inhoud van 200 m³. Door het groeiende te strooien areaal in Assen is de opslagcapaciteit van de huidige silo steeds in mindere mate toereikend. De kans dat de opslag leeg raakt moet, ook tijdens lang aanhoudend winterweer, geminimaliseerd worden. Daarom is besloten de opslagcapaciteit te vergroten door een extra zoutsilo te plaatsen. De inhoud van deze silo dient minimaal 250 m³ te zijn. Bekijk de aanbesteding »
Genoemde leveranciers: Aebi Schmidt Nederland BV
2016-01-20   Future Hemweg, Co-Firing Biomass Logistics 2016 (Nuon Power Generation B.V.)
The project Future Hemweg has the purpose to convert HW08 to a coal and biomass firing plant to increase renewable production in Employer's portfolio and reduce CO2 emissions. The required works, services and supply include but is not limited to, all installations (excluding underground Civil, silo concrete works and integration into existing automation lots) that are required for unloading barges, cleaning of wood pellets, storing of wood pellets. The scope comprises the engineering and design, … Bekijk de aanbesteding »
2015-11-04   Future Hemweg, Co-Firing Biomass Pneumatic feeding and mill conversion (Nuon Power Generation B.V)
The project Future Hemweg has the purpose to convert HW08 to a coal and biomass firing plant to increase renewable production in Employer's portfolio and reduce CO2 emissions. The required works, services and supply include but is not limited to, all installations and buildings that are required for pneumatic transport of wood pellets to two modified coal mills of HW08, conversion of 2 existing coal mills and modification of 12 burners. The scope comprises the design, procurement, construction, … Bekijk de aanbesteding »
2015-10-19   Future Hemweg, Co-Firing Biomass Inbound Logistics and Storage (Nuon Power Generation B.V)
The project Future Hemweg has the purpose to convert HW08 to a coal and biomass firing plant to increase renewable production in Employer's portfolio and reduce CO2 emissions. The project consists of the facilities required for co-firing biomass in HW08. This tender includes, but is not limited to, all installations and buildings that are required for unloading barges, cleaning of wood pellets, storing of wood pellets. The scope comprises the engineering and design, procurement, construction, … Bekijk de aanbesteding »
2015-08-28   Zoutsilo t.b.v. gladheid-bestrijding — leveren en plaatsen (Gemeente Rijssen-Holten)
Het doel van deze offerteaanvraag is het afsluiten van een overeenkomst met 1 dienstverlener ten behoeve van het leveren en plaatsen (inclusief aanbrengen betonnen fundatie) van een houten zoutsilo t.b.v. gladheidsbestrijding. Bekijk de aanbesteding »
Genoemde leveranciers: Aebi Schmidt Nederland BV
2011-07-18   Hammermill Hemweg (Nuon Power Generation B.V.)
Nuon is currently developing a biomass co-firing installation for its existing pulverized coal power plant, Hemweg 08 (HW08), in Amsterdam, The Netherlands (further: plant). The project encompasses the development of all facilities required for co-firing 14 % e/e biomass in HW08 (Phase 1). The biomass is clean wood in the form of pellets only (white pellets). In the future employer will expand the plant capacity to 28 % e/e biomass co-firing (phase 2). The plant is designed for phase 1, those parts of … Bekijk de aanbesteding »
Genoemde leveranciers: Geldof