In March 2019 a tender will be published. The objective of this tender is to conclude an agreement with a tenderer who is able to carry out the geophysical investigations required to obtain the soil information at the Wind Farm Zone Ten Noorden van de Waddeneilanden (TNW). The intention is to carry out the field work in the months July/August/September 2019. This soil information will be made available to all potential bidders for offshore wind farms in the Netherlands. The objective of the geophysical soil investigation is to improve the bathymetrical, morphological and geological understanding of the wind farm zone and identification of objects in the designated wind farm zones. The objective is also to obtain geophysical information on these locations, which is suitable for the preparation of geotechnical investigations and suitable to progress the design and installation requirements for offshore wind farms, including, but not limited to foundations and infield cables.
Deadline
De termijn voor de ontvangst van de offertes was 2019-04-26.
De aanbesteding werd gepubliceerd op 2019-03-15.
Leveranciers
De volgende leveranciers worden genoemd in gunningsbesluiten of andere aanbestedingsdocumenten:
Object Toepassingsgebied van de aanbesteding
Titel:
“Geophysical Survey at the Wind Farm Zone Ten Noorden van de Waddeneilanden (TNW)
201901057”
Producten/diensten: Dienstverlening door ingenieurs📦
Korte beschrijving:
“In March 2019 a tender will be published. The objective of this tender is to conclude an agreement with a tenderer who is able to carry out the geophysical...”
Korte beschrijving
In March 2019 a tender will be published. The objective of this tender is to conclude an agreement with a tenderer who is able to carry out the geophysical investigations required to obtain the soil information at the Wind Farm Zone Ten Noorden van de Waddeneilanden (TNW). The intention is to carry out the field work in the months July/August/September 2019. This soil information will be made available to all potential bidders for offshore wind farms in the Netherlands. The objective of the geophysical soil investigation is to improve the bathymetrical, morphological and geological understanding of the wind farm zone and identification of objects in the designated wind farm zones. The objective is also to obtain geophysical information on these locations, which is suitable for the preparation of geotechnical investigations and suitable to progress the design and installation requirements for offshore wind farms, including, but not limited to foundations and infield cables.
1️⃣
Aanvullende producten/diensten: Diensten voor technische testen, analyse en adviezen📦
Aanvullende producten/diensten: Geologie, geofysica en andere vormen van wetenschappelijke prospectie📦
Plaats van uitvoering: Nederland🏙️
Hoofdlocatie of plaats van uitvoering: The Wind Farm Zone Ten Noorden van de Waddeneilanden
Beschrijving van de aanbesteding:
“More about the exact scope of the assignment will be shared in the final tender document.” Gunningscriteria
Kwaliteitscriterium (naam): Award criterion relating to project documentation
Kwaliteitscriterium (weging): 22
Kwaliteitscriterium (naam): Award criterion relating to qualifications of personnel
Kwaliteitscriterium (weging): 15
Kwaliteitscriterium (naam): Award criterion relating to vessel(s), equipment and team
Kwaliteitscriterium (weging): 35
Kwaliteitscriterium (naam): Award criterion relating to cycle times
Kwaliteitscriterium (weging): 10
Kwaliteitscriterium (naam): Sustainable campaign execution
Kwaliteitscriterium (weging): 3
Prijs (weging): 15
Duur
Startdatum: 2019-06-12 📅
Einddatum: 2020-03-31 📅
Procedure Soort procedure
Open procedure
Administratieve informatie
Eerdere publicatie betreffende deze procedure: 2019/S 025-055484
Termijn voor de ontvangst van inschrijvingen of verzoeken tot deelneming: 2019-04-26
13:00 📅
Talen waarin inschrijvingen of aanvragen tot deelneming kunnen worden ingediend: Engels 🗣️
Het onderstaande tijdschema is uitgedrukt in aantal maanden.
Minimumtermijn gedurende welke de inschrijver de offerte gestand moet doen: 4
Voorwaarden voor de opening van de offertes: 2019-04-26
14:00 📅
Award Aankondiging (2019-07-05) Object Toepassingsgebied van de aanbesteding
Totale waarde van de opdracht (exclusief BTW): EUR 1960404.98 💰
Beschrijving
Hoofdlocatie of plaats van uitvoering: The Wind Farm Zone Ten Noorden van de Waddeneilanden.
Procedure Administratieve informatie
Eerdere publicatie betreffende deze procedure: 2019/S 056-129667
Gunning van het contract
1️⃣
Contractnummer: 1
Titel:
“Geophysical Survey at the Wind Farm Zone Ten Noorden van de Waddeneilanden (TNW)”
Datum van sluiting van het contract: 2019-06-17 📅
Informatie over aanbestedingen
Aantal ontvangen offertes: 3
Aantal elektronisch ontvangen inschrijvingen: 3
Naam en adres van de contractant
Naam: MMT Sweden AB
Postadres: Sven Källfelts Gata 11
Poststad: Västra Frölunda
Postcode: 426 71
Land: Zweden 🇸🇪
Telefoon: +46 317620306📞
E-mail: arent.vanderveen@mmt.se📧
Fax: +46 317620301 📠
Regio: 00 🏙️
URL: http://www.mmt.se🌏
De aannemer is een KMO
Informatie over de waarde van de opdracht/het perceel (exclusief BTW)
Totale waarde van het contract/perceel: EUR 1960404.98 💰
Bron: OJS 2019/S 130-319976 (2019-07-05)