Reassessment of designated pressure equipment Eemshaven

N.V. Nuon Energy

The NUON plants (3 Combined-Cycle Units and 1 Auxiliary Unit) installed at Eemshaven are scheduled for reassessment in 2017. This will be a reassessment of designated pressure equipment in accordance with the Dutch rules and regulations of the Pressure Equipment Commodities Act Decree. The main components of the reassessment are: — The 2-yearly reassessment of the heat recovery steam generator (HRSG) — The 4-yearly reassessment of pipes and vessels.

Deadline
De termijn voor de ontvangst van de offertes was 2016-07-22. De aanbesteding werd gepubliceerd op 2016-06-22.

Wie?

Wat?

Waar?

Aankoopgeschiedenis
Datum Document
2016-06-22 Aankondiging van een opdracht