IOS DE 2013 Gas coolers
General
The specifications for the gas coolers will be ready in the next phase of this European tender: the request for proposal.
The optional requirements for Rysum and Wardenburg will be decided in the course of 2013.
Gas coolers
The process gas coolers must secure an adjusted defined outlet temperature by means of frequency converter speed controlled low noise fans.
Scope:
- Design code: PED, AD 2000, ISO 13706;
- Compliance with- and fulfilling of applicable DVGW requirements and permit- noise requirements;
- Structural steel with working platforms, railings, self-closing passage gate, ladders, etc.;
- Foundation materials to be incorporated in the civil works;
- Control & instrumentation such as: Vibration switches, maintenance switches, cabling, cable trays in /on the process gas cooler, terminal boxes;
- Grilles of the air boxes, connections to earthing system base, etc.;
- Frequency converter + MCC system cabinets, including installation;
- Planning delivery and mounting of cables from gas cooler components to terminal boxes;
- Supply civil drawings and data for design of foundations and foundation slabs, such as dimensions, loads, forces / torques;
- All required inspections, non destructive testings, certifications, and documentation to the satisfaction of the German Notified Body
- Delivery on site based on DDP;
- Responsible for unloading and placing the supplied equipment on the foundation created by the customer;
- The final assembly and commissioning of the process gas coolers,
- Scheduling/coordination of installation work on site with GUD/contractors.
- Delivery of as built documentation and manufacturing book.
Deadline
De termijn voor de ontvangst van de offertes was 2013-03-21.
De aanbesteding werd gepubliceerd op 2013-02-18.
Wie?
Wat?
Waar?
Aankoopgeschiedenis
Datum |
Document |
2013-02-18
|
Aankondiging van een opdracht
|